Callide Power Station
 

Release of Brady Heywood report and C3 cooling tower report

17 Jul 2024

CS Energy has today published the Brady Heywood Report into the 2021 Callide Unit C4 incident and Hartz EPM's investigation report into the 2022 Callide Unit C3 partial cooling tower collapse.

CS Energy’s Chair Adam Aspinall and CEO Darren Busine will deliver a statement at 10am this morning about these reports, alongside CS Energy’s action plan to bolster the safety, reliability and resilience of its operations.

Brady Heywood report into Callide Unit C4 incident (full report, excluding appendices) (PDF 27.9MB)

Hartz EPM report into partial collapse of Callide Unit C3 cooling tower (PDF 11.8MB)

Media enquiries: 07 3854 7399